This was an install only project for the main contractor, we were asked to install all bathroom accessories, Led mirrors and bedroom mirrors for 122 standard bedrooms and 7 DDA bedrooms. We also installed bathroom accessories, gym mirrors, corner guards and revision panels for the public areas and back of house at the hotel. Our 24 days onsite was split over approximately 4 months as bedrooms were completed and made available to us.
Project type: Hotel
Project location: Canterbury UK
Clients: Main Contractor
Time on site: 24 days
Items installed: 1676